Government & Community Housing Methamphetamine Remediation

A two-storey government housing property remediated and independently cleared after widespread methamphetamine contamination.

Project Summary

A government housing property had widespread methamphetamine contamination across both levels of the house. 

Independent testing found methamphetamine residue above the residential investigation level in all 12 sampled areas. Results ranged from 0.61 to 9.2 µg/100 cm², with the highest result recorded at the entrance. The assessment concluded that the contamination pattern was consistent with methamphetamine smoking throughout the property, and that remediation and independent validation were required before the house could be reoccupied. 

Contam Solutions was engaged through the government housing builder to complete the site safety work, needle sweep, rubbish removal and methamphetamine remediation. 

What Contam Did

Contam Solutions first completed the site safety planning, needle sweep and rubbish removal before the remediation work began. 

The remediation included removal of internal carpeting, HEPA vacuuming and surface preparation, detailed detergent cleaning and repeated chemical and water rinse cycles across the contaminated internal areas. 

The property then underwent a triple-wash methamphetamine remediation (detergent clean, remediation chemical and repeated rinse cycles) before being handed over for independent post-remediation validation. 

Key Project Facts

Property Two-storey residential dwelling
Sector Government & Community Housing
Client pathway Engaged through the government housing builder
Contamination type Methamphetamine residue from smoking
Areas tested 12 internal locations
Areas above residential level All 12 sampled areas
Contamination range 0.61–9.2 µg/100 cm²
Independent validation Carried out separately by an independent provider

Key Project Facts

01
Step 01

Review the independent assessment and remediation requirements.

02
Step 02

Prepare the Safe Work Method Statement (SWMS), Job Safety Analysis (JSA) and site safety documentation.

03
Step 03

Complete the needle sweep before clearance work begins.

04
Step 04

Remove rubbish and loose contents from the property.

05
Step 05

Remove internal carpeting.

06
Step 06

HEPA vacuum and prepare the contaminated internal surfaces.

07
Step 07

Complete the detailed detergent clean.

08
Step 08

Apply the methamphetamine remediation chemical.

09
Step 09

Complete repeated chemical and water rinse cycles.

10
Step 10

Complete the final clean and dry-down.

11
Step 11

Hand the property over for independent post-remediation validation.

How We Ran This Project

Contam managed the job from clearance through to remediation.

The work started with the needle sweep and rubbish removal before moving into the full methamphetamine remediation.

The work was coordinated through the government housing builder.

Contam worked directly with the builder throughout the project, with independent testing and validation completed separately. 

Outcome

The methamphetamine remediation was completed across the affected internal areas and the property achieved independent post-remediation clearance. 

Independent post-remediation sampling found all areas below the 0.5 µg/100 cm² residential investigation level. 

The property was then handed back, deemed safe for residential use following independent validation.

Project Photos

BEFORE

Internal condition of the property before remediation.

DURING

Genuine clearance or remediation image showing the scale of the internal works.

AFTER

Completed internal areas following remediation.

Related Services

Contact Contam Solutions

Speak with our team about your property remediation requirements and the next steps.