Clandestine MDMA Drug Lab Remediation

A confirmed clandestine MDMA laboratory remediated using a staged approach to reduce contamination, preserve recoverable building materials and prepare the site for independent validation.

Project Summary

A rural property in the Shepparton region contained a confirmed clandestine MDMA laboratory operating within the main living unit, with associated activities also extending into the shed and attached spaces.

Independent testing identified significant MDMA contamination across the property, including contamination throughout the living areas. Results ranged from 0.92 to 490 µg/100 cm², with the highest result recorded in the main living area.

The main concern was the contamination within the domiciled areas of the property. Under the Australian clandestine drug laboratory remediation guidance, domiciled and non-domiciled areas are assessed against different investigation levels, meaning contamination within the living areas required particular attention as part of the remediation strategy.

Contam Solutions was engaged to carry out the remediation using a staged approach designed to avoid unnecessary large-scale demolition. The strategy was to reduce contamination first, progressively test the affected areas and only move to targeted demolition where cleaning alone could not achieve the required outcome.

What Contam Did

Contam Solutions first reviewed the independent assessment and engaged an independent occupational hygienist to prepare the Remediation Action Plan (RAP), then prepared the Safe Work Method Statement (SWMS), Job Safety Analysis (JSA) and site controls required to safely undertake the work.

The remediation began with site clearance and make-safe works. Specialist trades completed the electrical isolation and the degassing and removal of air-conditioning equipment, while Contam removed contaminated contents where required. Contam also removed the chemical residues and waste associated with the clandestine operation before detailed surface remediation commenced.

Affected surfaces were HEPA vacuumed and treated using a staged chemical remediation process, with progressive testing used to assess whether further cleaning or targeted demolition of building materials was required.

Where contamination remained above the applicable investigation level after cleaning, targeted demolition of affected flooring, subfloor materials or other building elements was undertaken rather than moving immediately to full demolition.

Key Project Facts

Property Rural residential property with main living unit, shed and attached spaces
Contamination type MDMA contamination associated with a confirmed clandestine laboratory
Primary concern Widespread contamination through the domiciled living areas
Australian Government guideline level – residential 7 µg/100 cm²
Australian Government guideline level – commercial/industrial 130 µg/100 cm²
Highest MDMA result 490 µg/100 cm² (main living area)
Compared with residential guideline level 70 times higher
Council involvement Property subject to an Improvement Notice
Remediation strategy Staged remediation with progressive testing
Targeted demolition Used where contamination could not be reduced sufficiently by cleaning alone
Independent validation Carried out separately by an independent provider after remediation

For context, the Australian Government Clandestine Drug Laboratory Remediation Guidelines set surface investigation levels for MDMA of 7 µg/100 cm² in residential areas and 130 µg/100 cm² in commercial/industrial areas. 

Key Project Facts

01
Step 01

Review the independent assessment and contamination results.

02
Step 02

Engage an independent occupational hygienist to prepare the Remediation Action Plan (RAP).

03
Step 03

Prepare the Safe Work Method Statement (SWMS), Job Safety Analysis (JSA) and site safety documentation.

04
Step 04

Complete electrical isolation and make-safe works using specialist trades.

05
Step 05

Specialist trades degas and remove affected air-conditioning equipment.

06
Step 06

Clear the site and remove rubbish, loose contents and contaminated materials.

07
Step 07

Remove chemical residues and waste associated with the clandestine operation.

08
Step 08

HEPA vacuum and prepare the affected internal surfaces.

09
Step 09

Complete the initial remediation wash cycle.

10
Step 10

Complete Contam’s own progressive testing of floors, subfloors, walls and internal structures.

11
Step 11

Complete targeted demolition of flooring or building materials where contamination remained above the applicable investigation level.

12
Step 12

Complete further remediation of affected areas.

13
Step 13

Complete Contam’s final testing to confirm the property is ready for independent validation.

14
Step 14

Confirm which building materials could be retained and which required demolition.

15
Step 15

Hand the property over for independent post-remediation validation.

16
Step 16

Provide a completion report, together with the independent validation results, to the client for submission to Council.

How We Ran This Project

The remediation strategy was designed to avoid full demolition if possible.

Contam structured the works around staged remediation and progressive testing so demolition decisions could be based on actual results rather than assumptions. This approach meant the kitchen and all internal walls were successfully remediated and retained, along with approximately three-quarters of the flooring.

Only the areas directly involved in the manufacturing process needed demolition.

The bathroom and en suite were stripped out completely. In the main lab area, demolition was partial: the walls were remediated and only the flooring was removed.

Contam tested its own work before handover.

Progressive testing continued through the works and final testing was completed before the property went to independent validation, avoiding repeated validation rounds and the cost that comes with them.

The site had no operational water or power.

Contam had to plan the works around the lack of basic site services. Approximately 300 litres of water was transported to the property on three separate occasions to complete the remediation and rinse stages, and generators supplied power for the works.

The living areas were treated differently from the non-domiciled spaces.

Because the Australian Government guidelines apply different MDMA investigation levels to residential and commercial/industrial areas, the remediation strategy had to account for how each part of the property was used.

Outcome

The staged remediation strategy successfully avoided full demolition of the property, saving the client the cost of a full demolition and rebuild. 

The kitchen and all internal walls were retained, along with approximately three-quarters of the flooring. Demolition was limited to the bathroom and en suite, which were stripped out, and the flooring removed in the main lab area. 

The property achieved independent clearance following remediation. The completion report and validation results were provided to the client for submission to Council, and the Improvement Notice was removed. 

Project Photos

BEFORE

The condition of the main living area before remediation

Cluttered Living Room with Renovation Supplies

DURING

The staged works, cleaning, targeted removal

Toolamba Post Demo_5363

AFTER

Successfully retained and remediated after the works.